The Ministry of Transportation Works and Utilities in collaboration with the Recovery and Development Agency (RDA) continue road works funded under the Caribbean Development Bank (CDB) reconstruction and rehabilitation loan.
The final phase on existing road projects is asphalting for six road projects which will commence this Friday 15th October with Little Dix Hill.
Asphalting work will continue at various road project sites over the next week and a half and will require certain sections of the road network to be closed which will impact commuters.
The full schedule of works and road closure days and time schedule are outlined below.
Date |
Site |
Timeline |
Working Hours |
Traffic Arrangement |
Friday 15th Oct. 2021 |
Little Dix Hill |
Full Day |
9:00 a.m.- 6:00 p.m. |
Road Closure |
Saturday 16th Oct. 2021 |
Lower Hope Hill to Sabbath Hill |
Full Day |
7:00 a.m.- 6:00 p.m. |
Road Closure |
Sunday 17th Oct. 2021 |
Great Mountain Site #2 |
Full Day |
7:00 a.m.- 6:00 p.m. |
Road Closure |
Monday 18th Oct. 2021 |
Great Mountain Site #1 |
Half Day |
6:00 a.m. -10:00 a.m. |
Road Closure |
Friday 22nd Oct. 2021 |
Ballast Bay |
Full Day |
9:00 a.m.- 6:00 p.m. |
Road Closure |
Saturday 23rd Oct. 2021 |
Ballast Bay |
Full Day |
7:00 a.m.- 6:00 p.m. |
Road Closure |
Sunday 24th Oct. 2021 |
Bob's Gas Station |
Full Day |
7:00 a.m.- 6:00 p.m. |
Road Closure |
The motoring public is asked to take note of these dates and times and where necessary plan to use alternate routes and coordinate their commute accordingly.
Project notification signs will be placed at various junctions to further notify of road closures and traffic wardens will be onsite to assist with traffic movement.
The Ministry would like to thank the public for their patience as these road works are completed and as the Government fulfils its mandate of improving the road infrastructure throughout the BVI.
Persons are asked to stay tuned to media outlets and social media, particularly the Government’s and RDA’s Facebook and Instagram pages and websites for the latest traffic advisories. Any complaints about this project can be lodged with the RDA through its Grievance - Redress System (GRS). See Grievance Redress System (GRS) | The Official Website of the Virgin Islands Recovery and Development Agency (bvirecovery.vg) for more information.